By David Stokes, New Product Development and Innovation Professional
This is based on a paper I presented at a conference a couple of years back. I’ll try and provide a condensed version here of what I talked about, but you are welcome to download the pdf of the paper here.
OK – how many times have you gone to a meeting where an important decision needs to be made and:
- No one has prepared (or they weren’t provided with any information until 5 minutes before the meeting) and most of the meeting is taken up with trying to get everyone up to date rather than focusing on making the required decision....
- It ends up being what could be an endless discussion that goes off track (and then people have trouble remembering what they were actually meant to be deciding)....
- You run out of time and people start leaving for their next meeting, so a decision isn’t made...
- Key people don’t turn up, or you get a “cast of thousands” who want to voice their opinions... and the people that didn’t turn up try to overturn the decision that was made..
- The MD/CEO gets frustrated with lack of progress and ends up ends up making the decision him/her self, even though they may not necessarily be the person with the needed knowledge or experience
I’m pretty certain that most of you can relate to some of these (or maybe all of the above!). We’ll, I you’re not alone!! But alls not lost - there are some simple rules you can apply that can help to make decision making a lot more effective in you organisations. And as I mentioned last time, unless you are making quality decisions based on good information in a timely manner, no process will be fully effective!
So what are the attributes of effective decision making?
1. Early, Event-Based Decisions Add the Most Value
I think most of you would agree that the longer you delay a needed decision, the less effect that decision is going to have on the outcome – often you’ll end up in a “fire-fighting” situation. But on the other side of the coin, there’s no use trying to make specific decisions early on in the project when there isn’t enough information. So what should be happening is getting the decisions made at the required time. This is one of the main premises behind Stage-Gate, ie: there are a number of decisions that need to be made at different points in the NPD projects, ie: gates. And each during each of the stages, the team is collecting the information required for the upcoming gate.
2. Decisions are Complete
A decision that is complete is unambiguous (everyone should be clear on what decision was reached) and sticks (the decision doesn’t subsequently get overturned outside of the decision making forum). To help with this, here are some clearly defined decision outcomes:
- Go
The project team is given the green light to proceed through the next stage.
BUT – IT’S A 2-WAY STREET: the decision makers are also committing the required staff, capital, expenses, facilities, etc. I don’t know how many times in all of the organisations I’ve worked for where a decision is made to proceed, but the project is not given the resources needed to do it. So therefore, one of the key pieces of information the decision makers should be provided with is the resource requirements – the decision should be made based on the resource requirements.
- No-Go
This can happen for a number of reasons, eg: the project doesn’t fit the agreed strategy, the product doesn’t meet the agreed market requirements, isn’t technically feasible to develop or the organisation is not able to provide the required resources (refer my note above).
Now remember, this is actually a good outcome!! What the project team have actually identified is that the project, for any of the reasons mentioned above, is not going to be successful. The best decision could be to stop the project (or for the right reasons, it could be put on hold) and to focus the organisations resources on a product/project that is more likely to be successful. I know form first-hand experience, this is easier said than done trying to convince the project team that they have actually done a good thing by recommending that he project is stopped. But do take the effort to communicate it from a top level across the organisation of the good decision and great work the team has done.
- Redirect
This decision outcome is used when there is not enough information to make a Go or No-Go decision and/or the preparation is incomplete. Remember, the decision makers time is extremely valuable, so the call for a redirect is best done in advance so as to not waste people’s time.
I have also found that an additional decision outcome is needed – “Conditional-Go”. We all know that there might be a couple of relatively minor outstanding pieces of information that aren’t available in time. Just remember that the purpose of the gates and the required deliverables/information is to mitigate risk. But it some cases, the risk and resulting impact of not proceeding may exceed the risk and impact in proceeding with a piece of information outstanding eg: missing a critical time-window. So don’t ignore common sense, but at the same time, don’t ignore the risk – do something about it! A smart decision could be “Go”, but the project team are required to take certain actions to address the risk, eg: “Go, but you need to come back with the required information within 1 week”.
3. Decision Authority is Appropriate for the Decision Domain
Often there a different levels of decision making in an organisation, eg: deciding on strategy vs. deciding whether a project should proceed to the next stage. And in some organisations, the decision makers could be different people. A good example of this is where all we are meant to be deciding is whether a project should proceed to the next stage, but the discussion veers off onto questioning the company strategy. While the company strategy is very important, you have to ask yourself whether this is the right time and place to do this. You can imagine how unproductive it could get if that this became a regular occurrence at the many gate reviews that occur!
4. Clear, Unambiguous Information Forms the Basis for High Quality Decisions
Again, a 2-way street:
- The project team is responsible to provide the decision makers with the information they require to make a high-quality informed decision
- But the decision makers are equally responsible to make sure they have received the information they require to make the decision.
5. Decisions are Actionable
This probably comes from my project management days, but good meeting minutes (or Records of Decisions / RODs we called them at Navman) are extremely important, covering:
- The decision outcome, ie: Go, No-Go or Redirect
- Key discussion points
- Action items for the decision makers
- Action items for the project team
- The timing, resource needs, and deliverables for the next phase (with +/- tolerances)
6. Decision are Rapid
For most projects, they are working to a tight schedule. When a decision needs to be made, it needs to be made in a timely manner in order to not impact the project.
In order to make a good decision in a timely manner, it’s a matter of being prepared and focused.
The following diagram shows what needs to be done leading up to a gate review, the structure of the decision making meeting as well as what needs to be done after the decision has been made:

- Development Activities and Gate Review Deliverable Preparation
The material is prepared for the decision makers to aid them in making the decision. This should be defined by your NPD process – what information is required at the different stages of the process, eg: business case and supporting financial information.
- In preceding week
The material that has been prepared should be provided to the decision makers well in advance, eg: 1 week before the meeting. This will enable the decision makers to review the material, ask any questions and raise issues in advance, which should also be answered/resolved beforehand. This means that the meeting is focused on making the decision required without being taken off track or getting bogged down - there should not be any surprises at the gate review!
- Gate Review
The meeting itself is also very structured. It should be quite clear who is running the meeting and who is present. And you don’t want the “cast of thousands” at the meeting: it should be the person presenting summary information (often the project manager) and the decision makers. If other “interested parties” are present, there is a risk that they will take they will take the meeting off track – if they aren’t part of making the decision, they shouldn’t be there.
- Publish Record of Decision (ROD)
The decision is captured and then approved by each of the decision makers. This ensures that it is very clear what the decision was and who made the decision.
E. Post Gate review
After the gate review, the decision is communicated to the people that need to know. As mentioned earlier, the outcome might have been a “Conditional-Go”, meaning that there are a number of outstanding points that need to be addressed. These need to be followed up on as required.
7. Clearly Defined & Known Roles and Responsibilities
For decision making meetings to run smoothly, everyone present needs to understand their role and responsibilities for the meeting.
A. Decision makers
Who the decision makers are should be clearly understood within the organisation. Each decision maker will often have a certain area of responsibility, eg: Marketing, Engineering, Finance, Portfolio, etc. For their area of responsibility, they are to make judgement (Go, No-Go, or Re-direct) on the project being reviewed and highlight any issues to the other decision makers. But, as mentioned earlier, these issues should be brought up and addressed prior to the gate review – again, there should be no surprises at the gate review.
B. Presenter
This person will present the information to the decision makers and will often be the project manager.
C. Chairperson
The chairperson is often one of the decision makers anyway, but they are the “owner” of the decision making process and ensures that there is the organisational commitment and accountability to enable success of the projects. They should encourage active, open, and honest participation by other Decision makers and the presenter to bring issues to the table and address them during the review. And sometimes they may need to act as the tie-breaker when decision makers are deadlocked.
D. Facilitator
The facilitator is handy to organise the meetings, ensure that the documentation is provided in advance, the right people are present, the meeting keeps to the agenda and that the documentation (Record of Decision) is sent out after the meeting.
Lessons Learned
I learnt a lot from changing the way decision making was being done at Navman. But in most cases, it only reinforced why what I’ve talked about above are so important, but are worth reiterating:
- Live up to the Record of Decision
If the gate reviews are to avoid becoming a “rubber stamp”, the decision makers must be able to enforce the decisions it makes – the Record of Decision (ROD) is the key document to do this
- Don’t allow projects to work ahead of the next gate
The Gate Review process is an important mechanism to allow the decision makers to maintain control of the level of investment in a project as a function of risk and priority – allowing teams to work ahead of the next gate can undermine this level of control.
- Prepare, Prepare, Prepare
Good decisions require good preparation – by the team, preparing the gate review material, and by the decision makers, reviewing the material and providing feedback.
The gate review is for making decisions, not in-depth discussion on issues and solutions. It’s a good idea for the Project Manager to follow up with each decision maker one-on-one prior to the gate review to discuss gate content and issues prior to the gate review. There should be no surprises at the gate review.
- Be prepared to follow the rules
Gate material should be out on time and decision makers reviewed the material giving feedback to the Project Manager. The decision makers complain when the material doesn’t come out on time. The Project Manager complains that the decision makers don’t read the material before the gate review. It’s tough to balance following process vs. impact on project. But we need to “break the cycle”
- Follow-up on the ROD action items
Don’t let ROD action items “fall through the cracks”. Outstanding ROD action items should be reviewed at each gate review.
- The ROD should be completed and sent out within 48 hrs of gate meeting
The ROD has most effect while the gate review is fresh in people’s minds. Some action items resulting from the gate review may have time urgency, so they need to be communicated ASAP.
OK – that’s decision making. I bet you didn’t think there was so much to it! But don’t underestimate the huge improvements that it can make to the way your organisation operates. But it’s not easy – the decision makers are often the most senior people – pulling them back into line is tricky. So make sure they all buy into this – it’s got to come from the top!